Seabridge Gold Inc. (TSX: SEA; NYSE: SA) says the BC Supreme Court has released a ruling settling the court orders in the challenges to the Substantially Started Designation (SSD) for its KSM Project in northwest BC. The court ruled that when it sent the SSD back to the BC Environmental Assessment Office (EAO) for reconsideration, it quashed the designation.
Seabridge says the ruling does not affect the status of KSM's environmental assessment certificate. If the EAO again concludes that KSM was substantially started, the certificate stays in place and will not be subject to expiry. KSM first received the SSD on July 24, 2024.
In its reconsideration, the EAO will also look at work done at KSM between July 24, 2024 and July 29, 2026. Seabridge says that data, submitted in September, raises construction investment at the project from $444 million to more than $700 million.
The SSD was challenged by the Tsetsaut Skii km Lax Ha (TSKLH) and SkeenaWild Conservation Trust. A June 8, 2026 ruling required a further 90-day consultation with the TSKLH, which ended September 28. The court has now dismissed the SkeenaWild petition without ruling on whether the SSD was reasonable, and has ruled on how much consultation with the TSKLH the reconsideration requires.
The company says the Tahltan and Nisga'a Nations continue to strongly support KSM. Seabridge will ask the EAO whether the ruling changes its timeline and is encouraging a prompt decision. "The legal status of KSM has not changed as of the November Ruling," said Chair and CEO Rudi Fronk.
Source: Seabridge Gold Inc. news release, November 19, 2026 (Newsfile). Read the full release.