White Gold Corp. has filed the independent preliminary economic assessment (PEA) for its White Gold project, about 95 kilometres south of Dawson City. At a base-case gold price of US$3,600 per ounce, the filed study shows an after-tax net present value (5%) of $1,856 million, a 41% after-tax internal rate of return and a 1.5-year payback, for a 9.4-year open-pit operation processing 12,000 tonnes per day and averaging 188,000 ounces of gold a year (223,000 ounces a year over the first five years). At US$4,500 gold, the after-tax NPV rises to $2,911 million with a 57% IRR.
The filed figures differ from those the company announced on August 10, when it reported an after-tax NPV of $1,911 million, a 38% IRR and a 1.7-year payback. As the company notes, a PEA is preliminary, relies in part on Inferred resources, and there is no certainty its results will be realized.
Source: White Gold Corp. news release, September 25, 2026, via Newsfile. Read the full release.